Regulator, company at odds over erosion, hillside slips
-
Wolf administration grants all of Energy Transfer's waiver requests
-
Company says state has allowed some work to continue.
-
Construction on the Mariner East pipeline appears to be halted by Gov. Wolf’s new order that shuts down all “non-life-sustaining” operations and businesses.
-
Tom Wolf, a Democrat, addressed the situation for the first time Wednesday afternoon, saying he is not aware of any wrongdoing.
-
Pennsylvania's Public Utility Commission demanded information from Sunoco Pipeline last year about what would happen if its Mariner East natural gas liquids pipelines failed, according to a newly discovered letter.
-
For now, independent pipeline experts say the blast appears to have been caused by the relighting of a pilot in a flare used by Sunoco for burning off excess gases, at a time when vapor had accumulated there.
-
The company did not explain what caused the backfire but apologized for the noise, which alarmed neighbors and fueled longstanding concerns about the safety of the new pipelines, which carry highly volatile natural gas liquids.
-
Demand for natural gas is growing across the Northeast. Meanwhile, natural gas production is booming in Pennsylvania. Connecting the two requires building pipelines across New York State.
-
If approved, company will pay $200,000 fine and step up safety inspections of aging pipeline